Lean applied to Software Development – Stop Wastes and Defects

December 6th, 2009

rightWhen one looks at all the wastes, has to be the most obvious one. The cost and repercussions of finding varies depending on where in the cycle they’re found. found early on in the development are way less costly to resolve than found later on in the cycle; the most expensive being when applications are already in-production.

Additionally, depending on when the are found, can and do trigger other wastes like task switching, relearning etc.

Gunther Gerlach

Translating Product Backlog into Sprint Backlog

December 6th, 2009

z-cubes1Every time a project is initiated there is no understanding, time-consuming effort to write down all foreseeable tasks or requirements. Usually, a project writes down what is obvious, which is almost always more than enough for a first sprint. The is then allowed to grow and change as more is learned about the product and its customers.

Gunther Gerlach

Key Features for User Story Implementation

July 8th, 2009

z-stepswritten by gunther gerlach-2009

A user story describes desired functionality from the customer (user) perspective. A good user story describes the desired functionality, who wants it, and how and why the functionality will be used.

The define a User Story as Independent, Negotiable, Valuable, Estimable, Small, Testable. Let’s see what each one means:

Independent - One user story should be independent of another (as much as possible). Dependencies between stories make planning, prioritization, and estimation much more difficult. Often enough, dependencies can be reduced by either combining stories into one or by splitting the stories differently.

Gunther Gerlach

How does a Project Manager add value to an Agile Scrum team?

July 7th, 2009

z-share written by gunther gerlach-2009

Definition: Agile project management is as radically different from traditional project management as agile processes are different from traditional methodologies. Rather than plan, instruct and direct, the agile facilitates, coaches and leads.

 

Recently I came across of someone posting about the value of a PM in an environment. It’s been a long time from most of the companies realized the important role of PMs But it looks like some Scrum process consultants, after run out of ideas to justify the PM’s role, they just wants to get rid off them… big mistake

Gunther Gerlach

How to measure your team and project velocity?

May 16th, 2009

z-velocitywritten by gunther gerlach-2009

Velocity is a measurement of how much the team gets done in an iteration (called as Sprint in ). Velocity is what actually got done in the last iteration not what is planned and is calculated by the number of done in a certain sprint.

In Scrum it is measure in . Each feature in scrum is a story. A story has points. Points can be anything you come up with.

Examples are 1, 2, 4, 8 , 16

aa

Gunther Gerlach

When Done is Done in Agile Scrum

May 16th, 2009

rightwritten by gunther gerlach-2009

In management process, there are few needs to happen for the sprint (iteration) to be called done. There are at least three types of Definitions of done.

 

Story Definition of done

·      A Story definition of done would look like this.

·      All stories should have automated acceptance test.

·      The story should have working code supported by unit test that provide around 60 – 70 percent coverage.

·      The story should have well defined acceptance criteria.

Gunther Gerlach