Understanding Your Project Velocity

April 28th, 2009

velocitywritten by gunther gerlach-2009

is terminology from the  methodology and is basically the same concept as in more traditional methods.

 

How it works: Select a regular time period over which to measure . If you’re using fixed or iterations, use that time period. Otherwise you can use weeks, fortnights or months. It doesn’t really matter which as long as you’re consistent. Add up the estimates for all the tasks/deliverables/features in your chosen time period. It doesn’t matter whether the estimates are in days, hours or even in relative . Only include the estimates for any items that are 100% complete and signed off within the time period. Anything still in progress counts as zero, as there is no value in incomplete work.